Hut 8 Links Its One-Gigawatt Texas Campus Plan to December Audit

The company expects 700 megawatts of utility power in the first quarter of 2027; each campus phase has a 352-MW information technology lease with the same tenant.

Updated 2 min read
Utility transmission lines cross open land near the Beacon Point campus site in Texas. / EconoTimes.ai
Utility transmission lines cross open land near the Beacon Point campus site in Texas. / EconoTimes.ai

A Texas audit is central to Hut 8 Corp.'s plan for its one-gigawatt Beacon Point AI campus, while the company expects 700 megawatts of utility power to come online in the first quarter of 2027.

Hut 8 CEO Asher Genoot told investors Nov. 4 he expects an unconditional baseload classification Dec. 17, which he said would bring the company closer to powering its full one-gigawatt campus. The designation remains subject to the audit. Chief Financial Officer Sean Glennan expects initial audit results Dec. 10, with the review to be finalized Dec. 17.

The utility-power target is separate from the campus's leased IT capacity. Hut 8 has contracted with the same tenant for 352 megawatts of information technology (IT) capacity in each phase. Initial data hall delivery is targeted for the third quarter of 2027 in Phase 1 and the second quarter of 2028 in Phase 2, with lease revenue beginning when the relevant capacity is delivered.

Hut 8 financed Phase 1 with $4.25 billion in project bonds and extended Phase 2's lease from 15 years to 17. As it arranges Phase 2 financing, the company said lenders can weigh two more years of contracted revenue, which may help cushion higher financing costs.

Hut 8 also increased its total share repurchase authorization to $1 billion from $250 million. It had already repurchased about $250 million in shares using proceeds from Bitcoin (BTC) sales; Genoot said the larger authorization did not signal immediate additional purchases. The company said it would cover the cost of campus electrical upgrades so residential ratepayers would not pay for them.

The next stated milestones are initial audit results on Dec. 10 and a Dec. 17 completion date that coincides with Genoot's anticipated baseload classification.